Walk the boardwalk past Ventura Place these days and you'll see it before you see Belmont Park itself: a 30-foot metal tower, all exposed steel and scaffolding, standing where the old lifeguard station used to lean and crack. It went up fast. It looks temporary. The city describes it as temporary, though the tower may remain in place for years while plans for Belmont Park next door await permits and a groundbreaking date.
This summer's boardwalk story includes two projects within a few hundred feet of each other at the south end of Mission Beach: the lifeguard tower is already operating, while Belmont Park's redevelopment remains in planning.
The tower that got built in three months
The old South Mission lifeguard tower had been falling apart for a decade, with fissures running along its exterior and rusted metal framing visible on the roofline. In March 2026, the city fenced it off after engineers flagged it as unsafe and began building a replacement just north of the original structure. By June, a new 30-foot steel tower and office trailer were standing in its place, up and running as a fully staffed, year-round lifeguard station rather than a seasonal setup.
That speed matters because of what this particular stretch of sand actually handles. The South Mission station logs an average of 69,500 preventative encounters and roughly 1,500 water rescues every year, more than any other lifeguard post in the city. One lifeguard summed up the station's reputation in blunt terms to Times of San Diego: it's known among lifeguards as the busiest one they've got.
The total cost to keep that operation running, including the tower, the office trailer, structural assessments, and emergency stabilization of the old building, comes to close to $4 million. A separate, far larger plan exists to replace all of it with a permanent $25 million lifeguard headquarters, complete with new locker rooms, a gym, and a garage. That plan is fully designed. It is not funded. City officials have said publicly that the temporary steel tower will likely remain standing over the boardwalk for years while they look for the money.
You can read the city's own project page on the South Mission Beach lifeguard station for the full scope of what the eventual permanent building is meant to include.
What that looks like next to Belmont Park's plans
Here's where the contrast gets sharper. A few hundred feet south, Belmont Park has been talking about its own overhaul since at least 2024, when reporting at the time described management hoping to have the bulk of a redevelopment ready for the public by 2026. That target has already slipped once. As of an April 2026 update, the roughly $20 million project still needed sign-off from the California Coastal Commission and the city before anyone could break ground, with management now aiming for a 2026 groundbreaking and a 2027 completion, assuming approvals come through on schedule.
The plan itself is genuinely interesting. According to CBS 8's coverage of the project, it would tear down the interior walls separating Belmont Park's arcade, midway, and beachfront into one open, indoor-outdoor space, sometimes described as a "barcade," where you could play vintage games with a drink in hand and see straight through to the sand. The longstanding Beach House restaurant would get gutted and reimagined, replacing most of its sandy floor with decorative concrete, patios, and small pools. Paired with existing spots like Draft House Belmont Park and Belmonty's Burgers, the plan would meaningfully expand what's available to eat and drink inside the park's footprint.
As of the most recent public update, none of it had broken ground. Here's the comparison, side by side:
| Temporary lifeguard tower | Belmont Park overhaul | |
|---|---|---|
| Estimated cost | About $4 million | About $20 million |
| Approval needed | City capital project, no outside approval required | California Coastal Commission and city permitting, still pending as of April 2026 |
| Time from announcement to reality | Fenced off March 2026, tower operating by June 2026 | First targeted for 2026 completion in 2024 reporting; now targeting a 2026 groundbreak and 2027 finish |
| Current status | Built, staffed, in daily use | Renderings and plans, construction not yet started as of April 2026 |
The temporary tower is standing today; Belmont Park's renovation remains at the planning stage.
What's already real at Belmont Park
Belmont Park has also seen completed improvements. The Giant Dipper, the century-old wooden roller coaster that anchors the park, underwent a genuine $1.6 million rehabilitation that wrapped in February 2026, with crews replacing worn wood throughout the track ahead of the coaster turning 101 this past July. The ride has been running smoother since, and anyone who's ridden it this year has been riding freshly rebuilt track, not the same boards that had been in place for a century.
A new Shipwreck Cove play area also opened near the coaster in late 2025, a free structure built for kids ages five to twelve, sitting adjacent to the Shipwreck Cove ride. It's a small addition, but it's finished and it's free, which puts it in a different category from the barcade concept still waiting on approval.
What it actually feels like on a walk right now
For anyone walking Ocean Front Walk this summer, the practical effect is a stretch of boardwalk that reroutes around active construction near Ventura Place, with a temporary walkway installed on the sand side of the seawall so foot traffic can get around the fenced-off sections. It's not a major detour, but it's noticeable if you've walked this route for years and know exactly where the pavement used to run straight.
The good news is that none of this touches the boardwalk's food and drink scene, which keeps doing its own thing regardless of what's happening with steel or permits. Cannonball, up on Belmont Park's own rooftop terrace, has a 180-degree ocean view and a sushi menu built around rolls like the Baja Bound, tuna and avocado with a serrano habanero kick, so you can watch the whole construction situation unfold from above while eating. Down at the corner of Santa Clara Court and Mission Boulevard, Miss B's Coconut Club leans into a tiki bar concept with drinks served in pineapple mugs and flamingo-shaped punch bowls, plus a rotating list of local and microbrew taps. Molly's, known for house-roasted coffee and a from-scratch pastry program, is the easier daytime stop if you want a croissant before a walk rather than a rum punch after one.
What the timelines show
The two projects have moved on different timelines. The lifeguard station replacement was built quickly out of practical necessity, while Belmont Park's redevelopment awaits a commission vote.
For residents who remember the old lifeguard tower before it was fenced off, the replacement marks a visible change to a familiar stretch of boardwalk.
If you're the kind of person who tracks these shifts because you like knowing your neighborhood better than the tourist guides do, Emily Schaefer spends a fair amount of time walking this same stretch of boardwalk and is always up for comparing notes over coffee. Schedule a personalized consultation whenever you'd like to talk through what else is changing along the coast this year.